WAEC offline past questions - with all answers and explanations in one app - Download for free
WAEC May/June 2024 - Practice for Objective & Theory - From 1988 till date, download app now - 99995

Project Evaluation And Review Technique/Critical Path Method Network Scheduling Technique In A Building Construction Project

Type Project Topics (docx)
Faculty Engineering, Environment & Technology
Course Project Management Technology
Price ₦3,000
Buy Now
Key Features:
No. of pages: 226
WAEC May/June 2024 - Practice for Objective & Theory - From 1988 till date, download app now - 99995
WAEC Past Questions, Objective & Theory, Study 100% offline, Download app now - 24709
WAEC offline past questions - with all answers and explanations in one app - Download for free
Abstract:
In this study research, we have examined the Project Evaluation and Review Technique, PERT and the Critical Path Method CPM/Critical Path Analysis. CPA as Project Management tools, among others, and applied them to study the Electrical and Mechanical services contract of the School of Health Technology Building Project, FUTO, using Network Planning and Scheduling approach. We reviewed relevant past literature to ascertain the views of professionals in project management, and accordingly developed the complete Work Breakdown Structure, WBS, of the project into its minutest various activities with corresponding duration times and resources loading to arrive at the resulting Network Schedule.

We carried out the analysis to determine the critical and other paths, earliest and latest start and finish times, floats resource/man power loading and smoothing and other critical indices. We showed that the potential problem of -he contractor, and in reality contractors, not using PERT/CPM Network technique led or would lead to project slip and time and cost overruns, all other things being equal. Finally, we re-examined and appraised the Bar/Gantt chart and PERT'CPM project planning techniques and recommended, in addition, efficient resource allocation/ scheduling method, use of experienced personnel and the application/use of personal computers with suitable programme packages to reduce the tedium of iterations.

KEY WORDS

Work Breakdown Structure; Scheduling; Network Structure; Critical Path; Project Evaluation and Review Technique; Building Construction Project; Lead and Lag time.
Buy Now
 
WAEC offline past questions - with all answers and explanations in one app - Download for free
WAEC Past Questions, Objective & Theory, Study 100% offline, Download app now - 24709
WAEC May/June 2024 - Practice for Objective & Theory - From 1988 till date, download app now - 99995