WAEC Past Questions, Objective & Theory, Study 100% offline, Download app now - 24709
WAEC May/June 2024 - Practice for Objective & Theory - From 1988 till date, download app now - 99995

An Assessment Of The Effect Of Cost Control Techniques On Building Project Delivery In Nigeria

Type Project Topics (doc)
Faculty Engineering, Environment & Technology
Course Quantity Surveying
Price ₦3,000
Buy Now
Key Features:
- No of Pages: 61

- No of Chapters: 04
JAMB CBT 2024 - Candidates, Schools, Centres, Resellers - Get Ready!
JAMB CBT Mobile App 2024 - Free Download
WAEC Past Questions, Objective & Theory, Study 100% offline, Download app now - 24709
WAEC May/June 2024 - Practice for Objective & Theory - From 1988 till date, download app now - 99995
Introduction:

Abstract



Despite the availability of various cost control techniques and assessment of the effect on building project techniques many construction projects still do not achieve their cost and time objectives. Research in this area so far has maini been devoted to identifying causes of cost and time overruns. There is limited research geared at studying factors inhibiting the ability of practitioners to effectively control their projects. To fill this gap, a survey was conducted on 250 construction project organisations in the UK, which was followed by face-to-face interviews with experienced practitioners from 15 of these organizations. The common factors that inhibit both time and cost control during construction projects were firstly identified. Subsequently 90 mitigating measures have been developed for the top five leading inhibiting factors-design changes, risks/uncertainties, inaccurate evaluation of project time/duration, complexities and non-performance of subcontractors were recommended. These mitigating measures were classified as: preventive, predictive, corrective and organizational measures. They can be used as a checklist of good practice and help project managers to improve the effectiveness of control of their projects.

Table of Content



TITLE PAGE

DECLARATION

CERTIFICATION

DEDICATION

ACKNOWLEDGEMENT

TABLE OF CONTENT

CHAPTER ONE

1.0 INTRODUCTION

1.1 BACKGROUND OF THE STUDY

1.2 AIM AND OBJECTIVES OF THE STUDY

1.3 SCOPE OF THE STUDY

1.4 DEFINATION OF TERMS

CHAPTER TWO

2.1 LITERATURE REVIEW

2.1.1 FACTORS AFFECTING THE CHOICE OF

BUILDING PROJECT DELIVERY IN NIGERIA

2.1.2 STATEMENT OF FACTS IN COST CONTROL TECHNIQUES

2.2 VARIOUS MATERIALS FOR WALL CONSTRUCTION

2.3 VARIOUS MATERIALS FOR WALL FINISHING

2.4 VARIOUS MATERIALS FOR FLOOR FINISHING

2.5 VARIOUS MATERIALS FOR CEILING FINISHING

2.6 VARIOUS TYPES OF ROOF COVERING

2.7 CONSTRUCTION OF CONCRETE

2.8 REINFORCEMENT TYPES

2.9 VARIOUS MATERIALS FOR DOORS

2.10 VARIOUS TYPES OF WINDOW

2.11 MECHANICAL INSTALLATION FITTINGS

2.12 ELECTRICAL INSTALLATION FITTINGS

2.13 MARKET SURVEY

2.14 CONSTRUCTION PROJECT

CHAPTER THREE

3.1 RESEARCH METHODOLOGY

3.2 ANALYSIS OF DATA

CHAPTER FOUR

4.1 SUMMARY

4.2 CONCLUSION

4.3 RECOMMENDATION

4.4 REFERENCES

4.5 QUESTIONNAIRE



Introduction

CHAPTER ONE

INTRODUCTION

1.1 BACKGROUND OF THE STUDY

In construction almost all clients are interested in obtaining fully functional facilities completed in time, cost, quality and scope. A builder who so able to construct within the estimated time and budget, to the right standards and scope is an excellent builder.



Cost control is a process where the construction cost of the project is managed through the best methods and techniques so that the cotr s nc suffer losses when carrying out the activities of the project. One of the aim of cost control is to construct at the cheapest possible costs consistent with the project objectives. Ultimately the decision of the manager that something should be done differently and the translation of that decision into practice are the actions to achieve control (Harris and McCaffer 2002).



Raina (1999) observes that it is of little use after a process has been completed to discover that its cost was actually too much. Most project managers and contractors in Nigeria find difficulty in controlling costs on their constructions sites due to a number of problems which include poor project preparation, lapse in management and control, over budgeting, poor materials, labour shortages, increased cost of materials, delays in deliveries, wastage of materials, unexpected whether changes, loss of materials, insecurity and poor communication.



This results into cost and time overruns, conflicts, and sometimes abandoning projects. This study was therefore carried out to identify the cost control techniques used in Nigeria and propose effective ones to building construction parties.



It specially worked at problems faced by the contractors in controlling the cost on site, studied the cost control techniques commonly used by the contractors during the construction stage and proposed remedies to be used by contractors on sites control their costs.
Buy Now
 
WAEC Past Questions, Objective & Theory, Study 100% offline, Download app now - 24709
JAMB CBT 2024 - Candidates, Schools, Centres, Resellers - Get Ready!
JAMB CBT Mobile App 2024 - Free Download
WAEC May/June 2024 - Practice for Objective & Theory - From 1988 till date, download app now - 99995