A project is estimated to take 300 hours but can be completed whenever the team has spare time. Three employees will take turns working on the project. The first employee completes one-third of the project. The second completes one-fifth of the work remaining. The third completes one-half of the work remaining. How many hours are left for the fourth employee to complete?