Job Arrival Time CPU Cycle
A 0 2
B 1 12
C 2 4
D...
Job Arrival Time CPU Cycle
A 0 2
B 1 12
C 2 4
D...
Job Arrival Time CPU Cycle
A 0 2
B 1 12
C 2 4
D 4 1
What is the Average Turnaround Time using FCFS?
A. 4.75 B. 6.5 C. 6.75 D. 11.5
What is the Average Turnaround Time using SJN?
A. 4.75 B. 6.5 C. 6.75 D. 11.5
What is the Average Turnaround Time using SRT?
A. 4.75 B. 6.5 C. 6.75 D. 11.5?