It takes 12 men 8 hours a day to finish a piece of work in 4 days. In how many days will it take 4 men working 16 hours a day to complete the same piece of work?

a

6 days

b

8 days

c

10 days

d

12 days

Download Offline App Ask a Question

Explanation

Correct Option
a

Video Explanation

Post your Contribution

Share:

Discussions (2)

Odemosad
1 year ago

If It takes 12 men 8 hours a day to finish a piece of work in 4 days,
Then, It'll take a man 12 x 8 x 4 = 384 days


For 4 men working 16 hrs a day i.e 4 x 16 x 1 = 64
Therefore, 384/64 = 6 days


Option A πŸ‘

Quick Questions

Ask a Question
LO

Lekman2027

14th August, 2025

Mathematics


3 comments

happysolomon

22nd June, 2026


1 comments
AF

Fifi53453

23rd June, 2026


1 comments