12 men complete a job in 9 days. How many men working t the same rate would be required to complete the job in 6 days?
a
24
b
18
c
12
d
9
e
8
Explanation
Correct Option
bVideo Explanation
No video available
Post your Contribution
Share:
Discussions (4)

marvelous2388
6 years ago
The answer is 18
1 man will do the work in 12×9=108 days
So 6 men will do it in 108÷6 = 18 days

Brixton
11 years ago
the answer is 18 because the more men you have, the less time it takes to do the job.
Answer:
9*12/6

nwuguru ezekiel
10 years ago
1 man will do it in 12*9days. (12*9)/6men will do it in 6days. the ans is 18