12 men complete a job in 9 days. How many men working t the same rate would be required to complete the job in 6 days?

a

24

b

18

c

12

d

9

e

8

Download Offline App Ask a Question

Explanation

Correct Option
b

Video Explanation

No video available

Post your Contribution

Share:

Discussions (4)

marvelous2388
6 years ago

The answer is 18
1 man will do the work in 12×9=108 days
So 6 men will do it in 108÷6 = 18 days

Brixton
11 years ago

the answer is 18 because the more men you have, the less time it takes to do the job.



Answer:

9*12/6

marvelous2388
6 years ago

The selected answer is wrong. Should be B.18

nwuguru ezekiel
10 years ago

1 man will do it in 12*9days. (12*9)/6men will do it in 6days. the ans is 18

Quick Questions

Ask a Question
CO

ceoofwahala

20th June, 2026

Chemistry


2 comments

ASSAAS

20th June, 2026

English Language


5 comments

infinitehoaxx

21st May, 2026

Computer


4 comments