Given: N
Direct material - 10 000
Direct labour - 5000
Direct expenses - 2000
Factory overhead - 4000
What is the prime cost?

a

N21 000

b

N 17 000

c

N 15 000

d

N 6 000

Download Offline App Ask a Question

Explanation

Correct Option
b

No explanation available

Video Explanation

No video available

Post your Contribution

Share:

Discussions (1)

Debbie14
5 years ago

Prime cost are cost that can be traced to the a particular production unit, they're directly related to the manufacturing process. These are direct materials, direct labour, direct expenses and other direct expenditure.
Prime cost=10,000+5,000+2,000=17,000

Quick Questions

Ask a Question
AF

Fifi53453

23rd June, 2026


1 comments

abdullahibabajide63

22nd June, 2026


1 comments
CO

ceoofwahala

20th June, 2026

Chemistry


2 comments